Features
Name |
MYNTRIANG SMALL HYDRO ELECTRIC PROJECT |
Total Capacity |
13.5 MW (3 x 3 MW + 3 x 1.5 MW) |
Location |
LENGERY, P.O. AMTRENG-782450, DIST: WEST KARBI ANGLONG |
Approach |
By Air |
125 KM from Guwahati Airport |
By Rail |
50 KMs from Kampur Junction |
By Road |
|
Date of Commissioning |
MSHEP-I |
Unit-I --- Commisioning realted work going on |
Unit-II --- Commisioning realted work going on |
Unit-III --- 16th February 2019 |
MSHEP-II |
Unit-I --- 08th August 2014 |
Unit-II --- 08th August 2014 |
Unit-III --- 18th May 2018 |
Beneficiary States |
Assam |
Technical Features |
Type of Fuel |
Water |
Source of Water for consumptive use |
TERENGLANGSO RIVER |
Turbine Type |
HORIZONTAL FRANCIS TURBINE |
Generator Type |
THREE-PHASE SYNCHRONOUS GENERATOR |
Evacuation System |
33 KV DOUBLE CIRCUIT LINE TO 220 KV KLHEP SWITCHYARD |
Achievements
Data Not Found
Generation Status
Financial Year |
Generation Status Stage-I in MU |
FY 2023-24 |
21.228 |
FY 2022-23 |
34.335 |
FY 2021-22 |
18.270 |
FY 2020-21 |
19.287 |
FY 2019-20 |
19.013 |
Financial Year |
Generation Status Stage-II in MU |
FY 2023-24 |
16.874 |
FY 2022-23 |
22.309 |
FY 2021-22 |
14.832 |
FY 2020-21 |
11.964 |
FY 2019-20 |
9.782 |